Harbour Energy has a 60 percent operated interest in PL032, which contains the fully-appraised Sea Lion field. We also have a 36 percent interest in PL004 with a farm-out proposed, which harmonises our interests across our licences in the Falkland Islands at 40 percent.

Our licences in the North Falklands Basin lie 220 kilometres north of the Falkland Islands.

In 2020, work on the Sea Lion Phase 1 pre-development project, which is aiming to develop 250 mmbbls of gross resource from PL032 using a conventional floating production storage offtake (FPSO) scheme, was suspended due to market conditions.

View electronic copies of the:

Sea Lion Environmental Impact Statement - full document
Sea Lion Environmental Impact Statement - non-technical summary

For full details of our licence interests in the Falkland Islands, see our global licence interests page.